Equinix Data Center IL2 & IL4

5 sets of  QSK-60 2500 ekW diesel engine system manufacture and erection.

Client: Cummins Turkey Motor ve Güç Sistemleri

Location: İstanbul – Türkiye

Year: 2023

Swissôtel Grand Efes İzmir

1 set CAT 2MW gas engine erection.

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İzmir – Türkiye

Year: 2023

Sakarya Gas Field Development Project

3 sets of Jenbacher J624 4498 ekW gas engine package manufacture and erection.

Client: TOPKAPI ENDÜSTRİ A.Ş.

Location: Zonguldak – Türkiye

Year: 2022

Swissôtel Grand Efes İzmir

1 set CAT 2MW gas engine disassembly works.

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İzmir – Türkiye

Year: 2022

İzmir Adnan Menderes Airport

1 set CAT 2MW gas engine disassembly works.

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İzmir – Türkiye

Year: 2022

TAI Subsonic Wind Tunnel

1 set of MTU 12V4000 Gx4 1250 ekW Dynamic UPS diesel engine manufacture and erection.

Client: MTU Motor Türbin A.Ş.

Location: Ankara – Türkiye

Year: 2022

Equinix Data Center IL2

1 set of  QSK-60 2500 ekW diesel engine system manufacture and erection.

Client: Cummins Turkey Motor ve Güç Sistemleri

Location: İstanbul – Türkiye

Year: 2022

Alperteks Cogeneration System

Erection of 1 Set MTU 20V4000L64 FNER 2538 gas engine, manufacture and erection of 3 sets heat recovery system and waste heat recovery boiler.

Client: MTU Motor Turbin A.S.

Location: Usak – Turkey

Year: 2021

ESA Grup Enerji Biogas Power Plant

Erection of 3 Set Jenbacher JMS-420 biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: Esa Grup Enerji

Location: Eskisehir – Turkey

Year: 2021

ESA Grup Enerji Biogas Power Plant

Erection of 2 Set Jenbacher JMS-420 biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: Esa Grup Enerji

Location: Ankara – Turkey

Year: 2021

ESA Grup Enerji Biogas Power Plant

Erection of 2 Set Jenbacher JMS-420 biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: Esa Grup Enerji

Location: Kayseri – Turkey

Year: 2021

ESA Grup Enerji Biogas Power Plant

Erection of 2 Set Jenbacher JMS-420 biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: Esa Grup Enerji

Location: İzmir – Turkey

Year: 2021

Beypiliç Yem Cogeneration System

Erection of 1 Set MWM TCG3016 V12 600 kWe gas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: Topkapı Endüstri A.Ş.

Location: Ankara – Turkey

Year: 2020

Beypiliç Kesimhane Cogeneration System

Erection of 2 Set MWM TCG2032 V16 4300 kWe gas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: Topkapı Endüstri A.Ş.

Location: Bolu – Turkey

Year: 2020

ESA Grup Enerji Biogas Power Plant

Erection of 2 Set Jenbacher JMS-320 biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: Esa Grup Enerji

Location: Manisa – Turkey

Year: 2020

KD Gübre

Erection of 1 Set MWM CG170-20 1560 ekW biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

İltekno Mühendislik Ticaret A.Ş.

Location: Eskişehir – Turkey

Year: 2019

ESA Grup Enerji Biogas Power Plant

Erection of 2 Set Jenbacher JMS-320 biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: TOPKAPI ENDÜSTRİ A.Ş.

Location: Manisa – Turkey

Year: 2019

ARF Enerji Biogas Power Plant

Erection of 1 Set GEJenbacher JMS-312 and 4 Set GEJenbacher JMS-320 biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: TOPKAPI ENDÜSTRİ A.Ş.

Location: Ödemiş / İzmir – Türkiye

Year: 2018

Maritaş Tekstil Cogeneration System

Erection of 1 Set MWM CG260-16 1560 ekW gas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kahramanmaraş – Türkiye

Year: 2018

ESA Grup Enerji Biogas Power Plant

Erection of 3 Set GEJenbacher JMS-320 biogas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: TOPKAPI ENDÜSTRİ A.Ş.

Location: Sincan / Ankara – Türkiye

Year: 2018

AHİ Enerji Biogas Power Plant

Erection of 2 Set GEJenbacher JMS-320 ve 3 Set GEJenbacher JMS-420 biogas engine, manufacture and erection of heat recovery system

Client: TOPKAPI ENDÜSTRİ A.Ş.

Location: : Suluova / Amasya – Türkiye

Year: 2018

Ve-Ge Kağıt Cogeneration Plant

Erection of 1 Set GEJenbacher JMS-620 gas engine, manufacture and erection of heat recovery system

Client: TOPKAPI ENDÜSTRİ A.Ş.

Location: Kemalpaşa / İzmir – Türkiye

Year: 2018

Midaş Tekstil Cogeneration System

Erection of 1 Set MWM CG260-16 4300 ekW gas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kahramanmaraş – Türkiye

Year: 2015

Matesa Tekstil Cogeneration System

Erection of 4 Set MWM CG260-16 4300 ekW gas engine, manufacture and erection of heat recovery system and waste heat recovery boiler

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kahramanmaraş – Türkiye

Year: 2015

TAI Cogeneration System

Erection of 4 Set MTU 2145 ekW gas engine, manufacture and erection of 16 barg heat recovery system and D-Type (steam and superheated water) waste heat recovery boiler

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Ankara – Türkiye

Year: 2014

Sabiya Power Plant Black Start System

6 set MTU 20V4000 2500 ekW diesel engine manufacture and erection.

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Sabiya – Kuwait

Year: 2014

Boufarik Power Plant Black Start System

7 set MTU 16V4000 2024 ekW diesel engine manufacture and erection.

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Boufarik – Algeria

Year: 2014

Medicana Hastanesi Cogeneration System

Erection of 1 Set MTU 849 ekW gas engine, manufacture and erection of heat recovery system

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Konya – Türkiye

Year: 2012

Acıbadem Hastanesi Cogeneration System

Erection of 3 Set MTU 849 ekW gas engine, manufacture and erection of heat recovery system

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Eskişehir / Kayseri / Adana – Türkiye

Year: 2012

Konya Şeker Cogeneration System

Erection of 1 Set MTU 1560 ekW gas engine, manufacture and erection of heat recovery system

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Konya – Türkiye

Year: 2011

Dr. Ahmet Hasyanesi Cogeneration System

Erection of 1 Set MTU 849 ekW gas engine, manufacture and erection of heat recovery system

MTU MOTOR TÜRBİN A.Ş.

Yer: İstanbul – Türkiye

Yıl: 2011

Başyazıcıoğlu Tekstil Cogeneration System

Erection of 1 Set MTU 2145 ekW gas engine, manufacture and erection of heat recovery system

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Kayseri – Türkiye

Year: 2011

Gümüştaş Madencilik Cogeneration System Sistemi

Erection of 1 Set MTU 2145 ekW gas engine, manufacture and erection of heat recovery system

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Gümüşhane – Türkiye

Year: 2010

Saray Halı Cogeneration System

Erection of 2 Set MTU 2145 ekW gas engine, manufacture and erection of heat recovery system

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Kayseri – Türkiye

Year: 2010

Selva Makarna Cogeneration Unit

Erection of 1 Set MTU 2145 ekW gas engine, manufacture and erection of heat recovery system

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Konya – Türkiye

Year: 2010

Hilton Hotel Cogeneration System

Erection of 1 Set MTU 1286 ekW gas engine, manufacture and erection of heat recovery system

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Bursa – Türkiye

Year: 2010

Durum Gıda Cogeneration System

Erection of 1 Set CAT 3516C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Mersin – Türkiye

Year: 2010

Orkide Yağ Factory Cogeneration System

Erection of 1 Set CAT 3516C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İzmir – Türkiye

Year: 2010

Naksan Tekstil Cogeneration System

Erection of 4 Set CAT 3520C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Gaziantep – Türkiye

Year: 2009

Melike Tekstil Cogeneration System

Erection of 1 Set CAT 3516C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Gaziantep – Türkiye

Year: 2009

Konya Şeker Cogeneration System

Erection of 1 Set CAT 3520C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İstanbul – Türkiye

Year: 2007

Botaş Cogeneration System

Erection of 1 Set CAT 3520C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Çorlu/Tekirdağ – Türkiye

Year: 2007

Polat Hotel Cogeneration System

Erection of 1 Set CAT 3516C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İstanbul – Türkiye

Year: 2007

Mauri Maya Fabrikası Cogeneration Units

Erection of container type 2 Set CAT 3520C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Bandırma / Bursa – Türkiye

Year: 2007

Pepsi Cola Cogeneration Units

Erection of container type 2 Set CAT 3520C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kazakistan

Year: 2007

Ormed II Cogeneration System

Erection of container type 5 Set CAT 3520C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kazakistan

Year: 2007

Kurtoğlu Alüminyum Cogeneration System

Erection of 2 Set CAT 3516B gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Çorlu / Tekirdağ – Türkiye

Year: 2006

Mardan Palace Cogeneration Units

Erection of container type 2 Set CAT 3516B gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Antalya – Türkiye

Year: 2006

Kilsan Tuğla Cogeneration System

Erection of 2 set CAT 3516C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İstanbul – Türkiye

Year: 2006

Four Seasons Hotel Cogeneration System

Erection of 1 set CAT 3516B gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İstanbul – Türkiye

Year: 2006

Coca–Cola Cogeneration System

Erection of 2 set CAT 3520 gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kazakistan

Year: 2006

Conrad Hotel Cogeneration System

Erection of 1 set CAT 3516C gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İstanbul – Türkiye

Year: 2005

Eroğlu Tekstil Cogeneration System

Erection of 1 set CAT 3516B gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Çorlu / Tekirdağ – Türkiye

Year: 2005

Küçükçalık Tekstil Cogeneration System

Erection of 4 set CAT 3520 gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Bursa – Türkiye

Year: 2005

Mercedes Benz Cogeneration System

Erection of 4 set CAT 3520 gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İstanbul – Türkiye

Year: 2004

Baydemir Tekstil Cogeneration System

Erection of 3 set CAT 3520 gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İstanbul – Türkiye

Year: 2004

Çelik Halat Cogeneration System

Erection of 2 set CAT 3516B gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kocaeli – Türkiye

Year: 2003

Tenghiz Chevron Oil Cogeneration Units

Erection of container type 2 Set CAT 3512 gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kazakistan

Year: 2003

Hurricane Cogeneration Units

Erection of container type 2 Set CAT 3508 gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kazakistan

Year: 2003

Tanrıverdi Tekstil Cogeneration System

Erection of 4 set CAT 3516B gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Çorlu / Tekirdağ – Türkiye

Year: 2003

Aktin Tekstil Cogeneration System

Erection of 4 set CAT 3520 gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Çorlu / Tekirdağ – Türkiye

Year: 2003

Saray Örme Tekstil Cogeneration System

Erection of 4 set CAT 3516B gas engine, manufacture and erection of heat recovery system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Bursa – Türkiye

Year: 2003

Dost İnşaat Tekirdağ Şehir Hastanesi Trigeneration System

3 set MTU 16V4000L64 2024 ekW gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system.

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Tekirdağ – Turkey

Year: 2019

Rönesans İnşaat İkitelli Şehir Hastanesi Trigeneration System

4 set MTU 20V4000L64 2535 ekW and 1 set MTU 16V4000L64 2024 ekW gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system.

Client: YANMAR TÜRKİYE MAKİNE ANONİM ŞİRKETİ

Location: İstanbul – Turkey

Year: 2019

YDA İnşaat Kayseri Şehir Hastanesi Trigeneration System

Erection of 2 Set MWM CG170-20 gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Kayseri – Türkiye

Year: 2018

YDA İnşaat Manisa Eğitim ve Araştırma Hastanesi Trigeneration System

Erection of 2 Set MWM CG132-12 gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Manisa – Türkiye

Year: 2018

Bilkent Entegre Sağlık Kampüsü Trigeneration System

Erection of 4 Set CG260-16 4300 gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Ankara – Türkiye

Year: 2016

Bursagaz Trigeneration System

Erection of 1 Set MAN E2876 E312 gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Bursa – Türkiye

Year: 2016

Ankamall AVM Trigeneration System

Erection of 3 Set MTU 20V4000L 2145 ekW gas engine, manufacture and erection of heat recovery system and multi chiller cooling system. Erection of heating and cooling lines between trigeneration plant and heat centers

Client: MTU MOTOR TÜRBİN A.Ş.

Location: Ankara – Türkiye

Year: 2015

Fatsa Devlet Hastanesi Trigeneration System

Erection of 2 Set MWM CG132-08 400 ekW gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Fatsa / Ordu – Türkiye

Year: 2015

Timsah Arena Trigeneration System

Erection of 1 Set CAT 3512E 1200 ekW gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: Bursa – Türkiye

Year: 2015

Sabiha Gökçen Havalimanı Trigeneration System

Erection of 2 Set CAT 3520C gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İstanbul – Türkiye

Year: 2009

TESCO Kipa Trigeneration System

Erection of container type 2 Set CAT 3516B gas engine, manufacture and erection of heat recovery system and absorption chiller cooling system

Client: BORUSAN GÜÇ SİSTEMLERİ A.Ş.

Location: İzmir – Türkiye

Year: 2008

MMK Atakaş Metalurji Energy Plant

Erection of Taurus 70 gas turbine, heat recovery system and waste heat recovery boiler.

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Kocaeli – Türkiye

Year: 2011

Delta Energy Waste Heat Recovery Boiler Erection

Erection of SG8 Type waste heat recovery boiler

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Lüleburgaz – Türkiye

Year: 2009

Kasar Dual Tekstil Energy Plant

Erection of Taurus 60 gas turbine, heat recovery system and waste heat recovery boiler

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Çorlu / Tekirdağ – Türkiye

Year: 2008

Altınmarka Gıda Energy Plant

Erection of M50 gas turbine, heat recovery system and waste heat recovery boiler

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: İstanbul – Türkiye

Year: 2008

Hayat Kağıt Energy Plant

Erection of Taurus 70 gas turbine, heat recovery system and waste heat recovery boiler

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Çorum – Türkiye

Year: 2004

Besler Gıda Waste Heat Recovery Boiler Erection

Erection of waste heat recovery boiler

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: İstanbul – Türkiye

Year: 2002

Can Tekstil Energy Plant

Erection of Taurus 60 gas turbine, economizer and waste heat recovery boiler

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Çorlu / Tekirdağ – Türkiye

Year: 2000

Zorlu Enerji A.Ş. Energy Plant

Erection heat recovery system

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: İstanbul / Bursa – Türkiye

Year: 1998

Maspo Alaşehir Geothermal Power Plant

Production of 1063 m³ capacity Fire Tank

Client: Maspo

Location: Manisa – Turkey

Year: 2019

Petro Peru Rafinerie de Talara

Pipe connections between waste heat recovery boiler and evaporator, documentation of ASME MDR. Inside piping of reactor

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Talara – Peru

Year: 2018

Söktaş Tekstil

Piping of washing machines, manufacture of boiler room condensate tank and general piping

Client: ASMAŞ AĞIR SANAYİ MAKİNALARI A.Ş.

Location: Aydın – Türkiye

Year: 2009-2010

Tarkim Kimya Proses Lines

Erection of process pipelines

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Bursa – Türkiye

Year: 2008

Eren Tekstil Energy Plant

Erection of 4 sets water heater

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Corlu / Tekirdag – Turkey

Year: 2007

EÜAŞ Tunçbilek Plant

Installation of sand filter rehabilitation of water preparation system

Client: SEGÜ MÜHENDİSLİK A.Ş.

Location: Kütahya – Türkiye

Year: 2006

Kroman Çelik A.Ş.

Erection and piping of water box (135 ton)

Client: ASMAŞ AĞIR SANAYİ MAKİNALARI A.Ş.

Location: Kocaeli – Türkiye

Year: 2006

İskenderun Demir Çelik

Manufacture of segment, erection of machine and piping of cooling water

Client: ASMAŞ AĞIR SANAYİ MAKİNALARI A.Ş.

Location: İskenderun – Türkiye

Year: 2006